Current Remediation Work

2019 Dredge Area Chart South2019 Dredge Area Chart North

Click on maps to view larger images.

Operations on the week of July 22:

  • The Mark Anthony (10" dredge) will continue to drege beyond the arc near the mouth of the river.
  • The Ottawa River (8" dredge) will complete operations in D135B and DMC15, then move to dredge between the Walnut Street bridge and Main Street bridge.
  • The John Deere (8" dredge) will dredge in DCA57, D47C DCC12 and D47H.